8.4 Revenue Recognized Over Time
ASC 606-10
25-27 An entity transfers control of a good or service over time and, therefore, satisfies a performance
obligation and recognizes revenue over time, if one of the following criteria is met:
- The customer simultaneously receives and consumes the benefits provided by the entity’s performance as the entity performs (see paragraphs 606-10-55-5 through 55-6).
- The entity’s performance creates or enhances an asset (for example, work in process) that the customer controls as the asset is created or enhanced (see paragraph 606-10-55-7).
- The entity’s performance does not create an asset with an alternative use to the entity (see paragraph 606-10-25-28), and the entity has an enforceable right to payment for performance completed to date (see paragraph 606-10-25-29).
ASC 606-10-25-27 is one of the most critical paragraphs in the standard since it effectively defines whether the entity is (1) providing the customer with a service (and revenue should be recognized as the entity is performing) or (2) providing the customer with a good (and revenue should be recognized only when the entity finishes what it was obligated to do and the good is transferred or delivered to the customer).
The criteria in ASC 606-10-25-27 were developed to provide an objective basis
for assessing whether control is transferred over time and, therefore, the
performance obligation is satisfied over time. The flowchart below summarizes the
criteria in ASC 606-10-25-27.
8.4.1 Meeting More Than One of the Criteria for Recognition of Revenue Over Time
The criteria in ASC 606-10-25-27 are not intended to be mutually
exclusive, and it is possible that an entity will meet more than one criterion.
For example, in some cases it may be determined that the “entity’s performance
creates or enhances an asset . . . that the customer controls as the asset is
created or enhanced” (ASC 606-10-25-27(b)) and that the entity also “does not
create an asset with an alternative use to the entity [and] has an enforceable
right to payment for performance completed to date” (ASC 606-10-25-27(c)).
When one or more of the criteria in ASC 606-10-25-27 are met,
revenue should be recognized over time.
8.4.2 Application of ASC 606-10-25-27 to Contracts With a Very Short Duration
For contracts with a short duration (e.g., a one-year contract
or a one-month contract), ASC 606 does not contain any practical expedient under
which entities would not be required to assess whether revenue should be
recognized over time or at a point in time but rather would simply default to
point-in-time recognition.
Entities should carefully analyze the contractual arrangement in
accordance with the requirements of ASC 606-10-25-27 to determine whether the
performance obligation is satisfied over time or at a point in time, even for
short-duration contracts. Depending on the timing of the transfer of control,
the distinction could result in different accounting outcomes when control is
transferred in multiple reporting periods. In addition, entities should consider
the different disclosure requirements related to those performance obligations
that are satisfied over time versus those that are satisfied at a point in
time.
8.4.3 Simultaneous Receipt and Consumption of Benefits of the Entity’s Performance
ASC 606-10
25-27 An entity transfers control of a good or service over time and, therefore, satisfies a performance
obligation and recognizes revenue over time, if one of the following criteria is met:
- The customer simultaneously receives and consumes the benefits provided by the entity’s performance as the entity performs (see paragraphs 606-10-55-5 through 55-6). . . .
55-5 For some types of
performance obligations, the assessment of whether a
customer receives the benefits of an entity’s
performance as the entity performs and simultaneously
consumes those benefits as they are received will be
straightforward. Examples include routine or recurring
services (such as a cleaning service) in which the
receipt and simultaneous consumption by the customer of
the benefits of the entity’s performance can be readily
identified.
55-6 For other types of
performance obligations, an entity may not be able to
readily identify whether a customer simultaneously
receives and consumes the benefits from the entity’s
performance as the entity performs. In those
circumstances, a performance obligation is satisfied
over time if an entity determines that another entity
would not need to substantially reperform the work that
the entity has completed to date if that other entity
were to fulfill the remaining performance obligation to
the customer. In determining whether another entity
would not need to substantially reperform the work the
entity has completed to date, an entity should make both
of the following assumptions:
-
Disregard potential contractual restrictions or practical limitations that otherwise would prevent the entity from transferring the remaining performance obligation to another entity
-
Presume that another entity fulfilling the remainder of the performance obligation would not have the benefit of any asset that is presently controlled by the entity and that would remain controlled by the entity if the performance obligation were to transfer to another entity.
The first criterion for determining whether a performance obligation is
satisfied over time (ASC 606-10- 25-27(a)) is that a customer simultaneously
receives and consumes benefits as the entity performs. This criterion most
commonly applies to typical service contracts, which would generally meet the
criterion. That is, the entity’s performance momentarily creates an asset that
the customer simultaneously receives and consumes, which means that the customer
obtains control of the entity’s output as the entity performs. Typically, in
contracts that meet the criterion in ASC 606-10-25-27(a), there is no tangible
asset that is being created by the accumulation of effort of the entity as it
performs. For example, a contract to provide a cleaning service and a contract
to process transactions on behalf of a customer are arrangements in which the
customer simultaneously consumes as the entity performs. That is, in each of
those examples, there is no accumulation of the entity’s efforts to build or
create an asset (e.g., a report, completed building, or piece of specialized
equipment). However, the customer does benefit from the entity’s efforts as the
entity performs; therefore, control of an asset is transferred to the customer
over time.
The FASB and IASB observed that determining whether the customer simultaneously receives and
consumes may be difficult in service-type contracts because the notion of “benefit” can be subjective.
Paragraph BC126 of ASU 2014-09 provides a shipping example in which an entity has agreed to
transport goods from Vancouver to New York City. Stakeholders questioned whether the customer in
that example receives any benefit as the goods are transported. ASC 606-10-55-6 notes that an entity’s
customer receives benefit as the entity performs if another entity would not need to substantially
reperform the work that the entity has completed to date to fulfill the remaining performance obligation.
ASC 606-10-55-6(b) clarifies that when assessing whether another entity would
not need to substantially reperform the work completed to date, an entity should
presume that the other entity would not be able to use the asset being used by
the current entity to fulfill the performance obligation. The boards observed
that if the goods in the shipping example described above were to be transported
only part of the way (e.g., to Chicago), another entity would not need to
substantially reperform what has already been performed even though that other
entity does not have the benefit of using the original entity’s truck to
transport the goods. Therefore, even though the new entity would need to use its
own truck to complete the fulfillment of the performance obligation, the
customer does in fact benefit from the original entity’s performance as the work
is performed (i.e., transfer of the goods from Vancouver to Chicago).
Consequently, the boards observed that assessing whether another entity would
need to substantially reperform the performance completed to date can be a good
indicator of whether the customer benefits simultaneously as the entity
performs. However, the boards also decided that in making this assessment, an
entity should disregard any contractual or practical limitations since the
objective of the criterion in ASC 606-10-25-27(a) is to determine whether
control of the goods or services has already been transferred to the customer.
That is, the entity would need to hypothetically assess what another entity
would need to reperform the work if the original entity were to stop performance
and let the second entity take over, regardless of actual practical or
contractual limitations. This hypothetical assessment would only be applicable
when the customer simultaneously receives and consumes as the entity performs;
such an assessment would not be appropriate for scenarios that meet either of
the other two criteria in ASC 606-10-25-27, which are discussed further
below.
ASC 606-10
Example 13 — Customer Simultaneously Receives and Consumes the Benefits
55-159 An entity enters into a contract to provide monthly payroll processing services to a customer for one
year.
55-160 The promised payroll processing services are accounted for as a single performance obligation in
accordance with paragraph 606-10-25-14(b). The performance obligation is satisfied over time in accordance
with paragraph 606-10-25-27(a) because the customer simultaneously receives and consumes the benefits of
the entity’s performance in processing each payroll transaction as and when each transaction is processed.
The fact that another entity would not need to reperform payroll processing services for the service that the
entity has provided to date also demonstrates that the customer simultaneously receives and consumes the
benefits of the entity’s performance as the entity performs. (The entity disregards any practical limitations on
transferring the remaining performance obligation, including setup activities that would need to be undertaken
by another entity.) The entity recognizes revenue over time by measuring its progress toward complete
satisfaction of that performance obligation in accordance with paragraphs 606-10-25-31 through 25-37 and
606-10-55-16 through 55-21.
Connecting the Dots
Stakeholders have raised questions regarding the
determination of when an entity transfers control of a commodity.
Specifically, they have questioned whether revenue related to the
delivery of a commodity should be recognized (1) at a point in time for
each commodity delivery or (2) over time because the entity is providing
a commodity delivery service of which the customer simultaneously
receives and consumes the benefits. In particular, the analysis in
question has focused on ASC 606-10-25-27(a), one of the three criteria
for determining whether revenue should be recognized over time.
For the criterion in ASC 606-10-25-27(a) to be met, the
customer must simultaneously receive and consume the benefits of the
good or service (e.g., the commodity) as the entity performs. The FASB
staff discusses this issue in Implementation Q&A 50 (compiled
from TRG Agenda Papers 43 and
44), noting that the evaluation of
the criterion in ASC 606-10-25-27(a) should take into consideration “all
relevant facts and circumstances, including the inherent characteristics
of the commodity, the contract terms, and information about
infrastructure or other delivery mechanisms.” In Implementation Q&A
50, the FASB staff further notes that the evaluation should be performed
in this manner “regardless of whether the contract is for the delivery
of a commodity or a widget.”
Accounting outcomes may differ if a multiperiod
commodity supply contract is viewed as individually distinct goods or
services (i.e., each individual delivery is a performance obligation
satisfied at a point in time) or as a series of distinct goods or
services of which the customer simultaneously receives and consumes the
benefits (i.e., delivery is part of a single performance obligation
satisfied over time). If the contract is determined to be for the
delivery of individually distinct goods or services (that do not qualify
to be accounted for as a series), the entity would need to allocate the
transaction price to each distinct good or service on a relative
stand-alone selling price basis. If the goods or services in the
contract are determined to be a series (i.e., a single performance
obligation satisfied over time), the entity would need to identify a
single measure of progress to determine the pattern of revenue
recognition.
An entity may need to evaluate whether the customer’s
action or intent to immediately receive and consume a commodity or use
the commodity later will affect whether the entity is able to conclude
that it meets the criteria for recognizing revenue over time (i.e., by
meeting the criterion that the “customer simultaneously receives and
consumes the benefits provided by the entity’s performance as the entity
performs”). Customers in certain industries (e.g., oil and gas, power
and utilities) may take different actions or have different intents for
the commodity delivered by the entity.
For example, a gas utility customer of an entity that
explores for and produces natural gas may store natural gas in a pool
until demand from its own customers requires the natural gas to be used.
Conversely, those same customers of the gas utility may not have
infrastructure with which to store natural gas in their homes and
thereby immediately receive and consume any natural gas delivered by the
utility (e.g., to heat a stove).
8.4.4 Customer Controls the Asset as It Is Created or Enhanced
ASC 606-10
25-27 An entity transfers control of a good or service over time and, therefore, satisfies a performance
obligation and recognizes revenue over time, if one of the following criteria is met: . . .
b. The entity’s performance creates or enhances an asset (for example, work in process) that the customer
controls as the asset is created or enhanced (see paragraph 606-10-55-7). . . .
55-7 In determining whether a
customer controls an asset as it is created or enhanced
in accordance with paragraph 606-10-25-27(b), an entity
should apply the guidance on control in paragraphs
606-10-25-23 through 25-26 and 606-10-25-30. The asset
that is being created or enhanced (for example, a work
in process asset) could be either tangible or
intangible.
The second criterion for determining whether a performance obligation is
satisfied over time (ASC 606-10-25-27(b)) is that the entity’s performance
creates or enhances an asset that the customer controls as the asset is created
or enhanced. This criterion was intended to address situations in which the
entity is creating an asset but it is clear that the customer controls the work
in process as the asset is created. Arrangements that would meet this criterion
for recognizing revenue over time include, but are not limited to, (1) a
renovation of, or addition to, the customer’s existing property and (2) the
configuration or customization of computer hardware and software owned by the
customer. Because the customer controls the work in process, the customer is
benefiting from the entity’s performance as the entity performs.
Example 8-1
Entity B enters into a contract to
manufacture a customized part for Customer L. To
manufacture the part, B must purchase the raw materials
from the supplier designated by L (i.e., B does not have
discretion to select the supplier). Entity B places
orders directly with the supplier, and it accepts and
takes legal title to the raw materials directly from the
supplier. The acceptability of the raw materials and
work in process is B’s responsibility, and the raw
materials and work in process stay in B’s physical
possession throughout the manufacturing process. Title
to the part, as well as the significant risks and
rewards of ownership of the part, is transferred to L
upon shipment of the part to L. The part is customized
to L’s specifications and has no alternative use to B.
However, B does not have an enforceable right to payment
and therefore fails to meet the criterion in ASC
606-10-25-27(c).
Entity B’s contract with L also does not
meet the criterion in ASC 606-10-25-27(b) for
recognizing revenue over time, as supported by the
following:
- Customer L does not accept, physically possess, or have title to the raw materials or work in process because B is manufacturing the customized part.
- Entity B has the risks and rewards of ownership of the raw materials and work in process until title to, and the risks and rewards of ownership of, the finished part are transferred to L.
- Although L has discretion in selecting the supplier for the raw materials, this does not give L control over the raw materials or the subsequent work in process.
The basis for the second criterion that the entity has in effect agreed to sell
its right to the asset as it performs (i.e., it is selling the work in process
to the customer as it performs).
However, in some instances, it may be unclear whether the asset being created or enhanced is
controlled by the customer, thus making it more difficult to determine whether this criterion is met.
Therefore, the boards developed the third criterion.
8.4.5 Entity’s Performance Does Not Create an Asset With an Alternative Use, and the Entity Has an Enforceable Right to Payment
ASC 606-10
25-27 An entity transfers control of a good or service over time and, therefore, satisfies a performance
obligation and recognizes revenue over time, if one of the following criteria is met: . . .
c. The entity’s performance does not create an asset with an alternative use to the entity (see paragraph
606-10-25-28), and the entity has an enforceable right to payment for performance completed to date
(see paragraph 606-10-25-29).
The third criterion (ASC 606-10-25-27(c)) was developed because the FASB and IASB observed that
applying the first two criteria could sometimes be challenging. In addition, the boards believed that there
are other scenarios economically similar to those described in ASC 606-10-25-27(a) and (b) in which an
entity’s performance is more akin to a service than the completion and delivery of a good. Paragraph
BC132 of ASU 2014-09 states that the boards regarded the third criterion as potentially necessary not
only “for services that may be specific to a customer (for example, consulting services that ultimately
result in a professional opinion for the customer) but also for the creation of tangible (or intangible)
goods.”
The boards believed that there are two mandatory features of arrangements that meet this criterion.
As a result, this criterion involves a two-part assessment (i.e., to meet the criterion, an entity must
demonstrate compliance with two subcriteria), which includes two notions: “alternative use” and “right to
payment.”
8.4.5.1 Alternative Use
ASC 606-10
25-28 An asset created by an entity’s performance does not have an alternative use to an entity if the entity
is either restricted contractually from readily directing the asset for another use during the creation or
enhancement of that asset or limited practically from readily directing the asset in its completed state for
another use. The assessment of whether an asset has an alternative use to the entity is made at contract
inception. After contract inception, an entity shall not update the assessment of the alternative use of an asset
unless the parties to the contract approve a contract modification that substantively changes the performance
obligation. Paragraphs 606-10-55-8 through 55-10 provide guidance for assessing whether an asset has an
alternative use to an entity.
55-8 In assessing whether an
asset has an alternative use to an entity in
accordance with paragraph 606-10- 25-28, an entity
should consider the effects of contractual
restrictions and practical limitations on the
entity’s ability to readily direct that asset for
another use, such as selling it to a different
customer. The possibility of the contract with the
customer being terminated is not a relevant
consideration in assessing whether the entity would
be able to readily direct the asset for another
use.
55-9 A contractual
restriction on an entity’s ability to direct an
asset for another use must be substantive for the
asset not to have an alternative use to the entity.
A contractual restriction is substantive if a
customer could enforce its rights to the promised
asset if the entity sought to direct the asset for
another use. In contrast, a contractual restriction
is not substantive if, for example, an asset is
largely interchangeable with other assets that the
entity could transfer to another customer without
breaching the contract and without incurring
significant costs that otherwise would not have been
incurred in relation to that contract.
55-10 A practical limitation
on an entity’s ability to direct an asset for
another use exists if an entity would incur
significant economic losses to direct the asset for
another use. A significant economic loss could arise
because the entity either would incur significant
costs to rework the asset or would only be able to
sell the asset at a significant loss. For example,
an entity may be practically limited from
redirecting assets that either have design
specifications that are unique to a customer or are
located in remote areas.
The notion of alternative use was developed to distinguish circumstances in
which the entity’s performance does not represent a service and therefore
would not result in the transfer of control to the customer over time. That
is, if the asset has an alternative use, the asset could readily be
redirected to another customer, which is commonly the case for standard
inventory-type items. In the case of inventory (readily redirected assets),
the production effort is not transferring a benefit to the customer as the
entity performs. The criterion in ASC 606-10-25-27(c) was intended to apply
to circumstances in which the entity creates a highly customized or
specialized asset that would be difficult to redirect to another customer
without incurring significant costs and performing additional work.
In making this assessment, the entity needs to consider both practical
limitations and contractual restrictions on redirecting the asset for
another use. For example, if the terms of the contract indicate that the
entity is prohibited from transferring the asset to another customer and
that restriction is substantive, the entity would conclude that the asset
does not have an alternative use because the entity is contractually
prohibited from redirecting the asset for another use. This is often the
case in real estate contracts; however, it may also occur in other types of
contracts, such as those involving the construction of highly specialized
assets.
On the other hand, contractual restrictions that provide the customer with a
protective right are not sufficient to establish that there is no
alternative use for the asset. Protective rights typically allow the entity
to substitute the asset, or redirect the asset, without the customer’s
knowledge. For example, terms of the contract may indicate that the entity
cannot transfer a good because the customer has legal title to the goods in
the contract; however, these terms may act merely as protection in the event
of liquidation, and the entity can then physically substitute the asset or
redirect it to another customer for little cost. This type of contractual
restriction is a protective right and would not be viewed as transferring
control to the customer.
An entity’s assessment of alternative use should be performed at contract
inception and should not be updated unless there is a contract modification
that substantively changes the performance obligation. In performing the
assessment, the entity should consider the asset in its completed state when
determining whether the asset can practically be readily redirected.
Further, in addition to concluding that there is no alternative use, the
entity must conclude that it has a right to payment for performance
completed to date, which is further described in Section 8.4.5.2.
ASC 606-10
Example 15 — Asset Has No Alternative Use to the Entity
55-165 An entity enters into a contract with a customer, a government agency, to build a specialized satellite.
The entity builds satellites for various customers, such as governments and commercial entities. The design
and construction of each satellite differ substantially, on the basis of each customer’s needs and the type of
technology that is incorporated into the satellite.
55-166 At contract inception, the entity assesses whether its performance obligation to build the satellite is a
performance obligation satisfied over time in accordance with paragraph 606-10-25-27.
55-167 As part of that assessment, the entity considers whether the satellite in its completed state will have an
alternative use to the entity. Although the contract does not preclude the entity from directing the completed
satellite to another customer, the entity would incur significant costs to rework the design and function of the
satellite to direct that asset to another customer. Consequently, the asset has no alternative use to the entity
(see paragraphs 606-10-25-27(c), 606-10-25-28, and 606-10-55-8 through 55-10) because the customer-specific
design of the satellite limits the entity’s practical ability to readily direct the satellite to another
customer.
55-168 For the entity’s
performance obligation to be satisfied over time
when building the satellite, paragraph
606-10-25-27(c) also requires the entity to have an
enforceable right to payment for performance
completed to date. This condition is not illustrated
in this Example.
Example 8-2
A manufacturer of automobile parts
enters into a contract with a customer for the
initial production of 1,000 parts for the customer’s
new vehicle. The parts are highly customized and
only compatible with the customer’s new vehicle
(i.e., the parts would not function in other
vehicles). The contract provides the manufacturer
with an enforceable right to payment for its
performance throughout the contract period in
accordance with ASC 606-10-25-27(c). There are no
contractual restrictions preventing the manufacturer
from redirecting the finished parts to a third
party. However, since an aftermarket for the parts
does not exist at contract inception and there are
no other customers to which the part can be readily
directed, the manufacturer is limited practically
from redirecting the parts for another use.
In this example, the contract for
the initial production of parts meets the criterion
in ASC 606-10-25-27(c) for recognizing revenue over
time. In accordance with ASC 606-10-25-27(c), an
entity is required to recognize revenue over time if
the asset being produced has no alternative use and
the entity has an enforceable right to payment. ASC
606-10-25-28 further requires an entity to determine
“at contract inception” whether the asset being
produced has an alternative use. Since the
manufacturer in this fact pattern is limited
practically from redirecting the parts for another
use (because no aftermarket exists at contract
inception), the parts do not have an alternative
use. Since the parts do not have an alternative use
and, as noted above, the contract provides an
enforceable right to payment for the manufacturer’s
performance throughout the contract period, the
criterion in ASC 606-10-25-27(c) would be met.
However, once an aftermarket for the parts does
exist, the manufacturer would be able to redirect
the parts to another party, thereby creating an
alternative use. At that point, the criterion in ASC
606-10-25-27(c) for recognizing revenue over time
would no longer be met for future contracts to
manufacture and deliver the parts (including any
modifications to the original contract that
substantively change the performance
obligation).
We acknowledge that in other
situations, a manufacturer of parts may believe that
it is highly probable that an aftermarket for the
parts will exist in the future (e.g., after the
development stage). In these situations, entities
will need to apply judgment and consider all of the
relevant facts and circumstances, including, but not
limited to, (1) historical evidence, (2) the
quantity of the parts, (3) the nature of the parts,
(4) the stage of development, (5) the existence of a
contract, and (6) contract negotiations. Entities
may want to consult with their accounting advisers
in such situations.
Connecting the Dots
In Implementation Q&A 55
(compiled from TRG Agenda Papers 56 and
60), the FASB staff discusses
whether an entity should consider the completed asset or the
in-production asset when performing the “alternative use” assessment
under ASC 606-10-25-27(c). The FASB staff’s analysis of this issue
is illustrated in the following example:
An
entity enters into a contract with a customer to build
equipment. The entity is in the business of building custom
equipment for various customers. The customization of the
equipment occurs when the manufacturing process is approximately
75% complete. In other words, for approximately 75% of the
manufacturing process, the in-process asset could be redirected
to fulfill another customer’s equipment order (assuming there is
no contractual restriction to do so). However, the equipment
cannot be sold in its completed state to another customer
without incurring a significant economic loss. The design
specifications of the equipment are unique to the customer and
the entity would only be able to sell the completed equipment at
a significant loss.
The FASB staff notes in Implementation Q&A 55
that “[b]ecause the entity [in the example] cannot sell the
completed equipment to another customer without incurring a
significant economic loss, the entity has a practical limitation on
its ability to direct the equipment in its completed state and,
therefore, the asset does not have an alternative use.” Accordingly,
regardless of the timing of the customization in the production
process (i.e., when the good has no alternative use), the entity
should consider whether the completed asset could be redirected to
another customer without the need for significant rework on the
customized good. If the completed asset is deemed to have no
alternative use, that aspect of the criterion in ASC 606-10-25-27(c)
would be met.
8.4.5.2 Enforceable Right to Payment for Performance Completed to Date
ASC 606-10
25-29 An entity shall consider the terms of the contract, as well as any laws that apply to the contract, when
evaluating whether it has an enforceable right to payment for performance completed to date in accordance
with paragraph 606-10-25-27(c). The right to payment for performance completed to date does not need
to be for a fixed amount. However, at all times throughout the duration of the contract, the entity must be
entitled to an amount that at least compensates the entity for performance completed to date if the contract is
terminated by the customer or another party for reasons other than the entity’s failure to perform as promised.
Paragraphs 606-10-55-11 through 55-15 provide guidance for assessing the existence and enforceability
of a right to payment and whether an entity’s right to payment would entitle the entity to be paid for its
performance completed to date.
55-11 In accordance with
paragraph 606-10-25-29, an entity has a right to
payment for performance completed to date if the
entity would be entitled to an amount that at least
compensates the entity for its performance completed
to date in the event that the customer or another
party terminates the contract for reasons other than
the entity’s failure to perform as promised. An
amount that would compensate an entity for
performance completed to date would be an amount
that approximates the selling price of the goods or
services transferred to date (for example, recovery
of the costs incurred by an entity in satisfying the
performance obligation plus a reasonable profit
margin) rather than compensation for only the
entity’s potential loss of profit if the contract
were to be terminated. Compensation for a reasonable
profit margin need not equal the profit margin
expected if the contract was fulfilled as promised,
but an entity should be entitled to compensation for
either of the following amounts:
-
A proportion of the expected profit margin in the contract that reasonably reflects the extent of the entity’s performance under the contract before termination by the customer (or another party)
-
A reasonable return on the entity’s cost of capital for similar contracts (or the entity’s typical operating margin for similar contracts) if the contract-specific margin is higher than the return the entity usually generates from similar contracts.
55-12 An entity’s right to
payment for performance completed to date need not
be a present unconditional right to payment. In many
cases, an entity will have an unconditional right to
payment only at an agreed-upon milestone or upon
complete satisfaction of the performance obligation.
In assessing whether it has a right to payment for
performance completed to date, an entity should
consider whether it would have an enforceable right
to demand or retain payment for performance
completed to date if the contract were to be
terminated before completion for reasons other than
the entity’s failure to perform as promised.
55-13 In some contracts, a
customer may have a right to terminate the contract
only at specified times during the life of the
contract or the customer might not have any right to
terminate the contract. If a customer acts to
terminate a contract without having the right to
terminate the contract at that time (including when
a customer fails to perform its obligations as
promised), the contract (or other laws) might
entitle the entity to continue to transfer to the
customer the goods or services promised in the
contract and require the customer to pay the
consideration promised in exchange for those goods
or services. In those circumstances, an entity has a
right to payment for performance completed to date
because the entity has a right to continue to
perform its obligations in accordance with the
contract and to require the customer to perform its
obligations (which include paying the promised
consideration).
55-14 In assessing the
existence and enforceability of a right to payment
for performance completed to date, an entity should
consider the contractual terms as well as any
legislation or legal precedent that could supplement
or override those contractual terms. This would
include an assessment of whether:
-
Legislation, administrative practice, or legal precedent confers upon the entity a right to payment for performance to date even though that right is not specified in the contract with the customer.
-
Relevant legal precedent indicates that similar rights to payment for performance completed to date in similar contracts have no binding legal effect.
-
An entity’s customary business practices of choosing not to enforce a right to payment has resulted in the right being rendered unenforceable in that legal environment. However, notwithstanding that an entity may choose to waive its right to payment in similar contracts, an entity would continue to have a right to payment to date if, in the contract with the customer, its right to payment for performance to date remains enforceable.
55-15 The payment schedule
specified in a contract does not necessarily
indicate whether an entity has an enforceable right
to payment for performance completed to date.
Although the payment schedule in a contract
specifies the timing and amount of consideration
that is payable by a customer, the payment schedule
might not necessarily provide evidence of the
entity’s right to payment for performance completed
to date. This is because, for example, the contract
could specify that the consideration received from
the customer is refundable for reasons other than
the entity failing to perform as promised in the
contract.
Right to payment is the second mandatory feature in the assessment of whether the criterion in
ASC 606-10-25-27(c) is met. The boards reasoned that if an entity is creating a highly specialized or
customized asset without an alternative use (i.e., the entity meets the first subcriterion in ASC 606-10-
25-27(c)), the entity would want to be economically protected from the risk associated with doing so.
Consequently, the boards incorporated the requirement of a right to payment into the third criterion for
assessing whether the entity is transferring control of the asset to the customer over time (i.e., providing
a service). In addition, the customer’s obligation to pay for performance completed to date indicates that
the customer has received some of the benefits of the entity’s performance.
For the purpose of evaluating the guidance in ASC 606-10-25-27(c), the right to payment refers to a
payment compensating the entity for performance completed to date and does not pertain to, for
example, a deposit or payment to compensate the entity for inconvenience or loss of profit in the event
of a termination. The right to payment for performance completed to date must include compensation
for costs incurred to date plus a reasonable profit margin. A reasonable profit margin does not
necessarily mean the profit margin that the entity would earn on the entire contract once completed
(i.e., if the contract were to be terminated at any point in time, the partially completed asset may not be
proportional to the value of the contract if it was completed). Rather, a reasonable profit margin should
be (1) based on a reasonable proportion of the entity’s expected profit margin or (2) a reasonable return
on the entity’s cost of capital.
Further, the right to payment must be an enforceable right to demand or retain payment, or both.
However, it does not need to be a present unconditional right to payment in the event that the
customer terminates the contract before the asset is fully completed.
If the customer pays a nonrefundable up-front fee, this could be viewed as a
right to payment if the entity is able to retain at least an amount for
performance completed to date in the event of a contract termination.
However, payment terms by themselves do not support a determination of
whether an entity has an enforceable right to payment for performance
completed to date. Rather, the entity should evaluate whether it has an
enforceable right to payment if the contract were to be terminated for
reasons other than the entity’s failure to perform. For example, an entity
may be paid only upon contract completion or may be paid entirely up front.
In those circumstances, the entity must consider whether it has a right to
demand or retain payment for performance completed to date if the contract
were to be terminated.
The FASB and IASB clarified that there may be instances in which an entity’s
customer does not have the right to terminate the contract, or only has the
right to terminate the contract at specified times, but the entity may still
conclude that it has an enforceable right to payment. Such instances may
occur if the contract or other jurisdictional laws require completion of
obligations by both the entity and the customer. This is often referred to
as the specific performance notion. Refer to Example 8-4 for an illustration of the
specific performance notion.
While an entity may conclude that it meets the criterion in ASC 606-10-25-27(c)
for recognizing revenue over time because it is creating an asset that does
not have an alternative use and it has the right to payment for performance
completed to date, recognition of revenue may not be appropriate for
materials purchased that are not yet incorporated into the asset. For
example, an entity may purchase raw materials that will be used as inputs to
satisfy the performance obligation, but the inputs are not yet transferred
to the customer through incorporation into the asset and therefore still may
be used for other purposes. The example below illustrates this concept.
Example 8-3
Entity X enters into a contract with
Customer Y under which X will construct an asset for
Y that has no alternative use to X. To build this
machine, X acquires standard materials that it
regularly uses in other contracts and manufactures
some “generic” component parts for inclusion in the
customer’s asset. These standard materials remain
interchangeable with other items until actually
deployed in the construction of the asset for Y.
If Y cancels the contract, X will be
entitled to reimbursement for costs incurred for
work completed to date plus a margin of 10 percent
(which is considered to be a reasonable margin in
accordance with ASC 606-10-55-11). However, X will
not be reimbursed for any materials (e.g.,
subcomponent parts) that have been purchased for use
in the contract but have not yet been used and are
still controlled by X.
Under ASC 606-10-25-27(c), revenue
from a contract should be recognized over time if
the “entity’s performance does not create an asset
with an alternative use to the entity . . . , and
the entity has an enforceable right to payment for performance completed to
date” (emphasis added).
The asset that X is constructing for
Y has no alternative use to X, and the terms of the
contract reimburse X for the costs of work completed
to date plus a reasonable margin. However, materials
(e.g., subcomponent parts that may be classified as
inventory) that have not yet been used are not part
of “performance completed to date”; therefore, there
is no requirement that the entity have an
enforceable right to reimbursement for such
items.
Under the contract termination
provisions, if the customer terminates the contract
early, X is entitled to payment of costs incurred
plus a reasonable profit margin. However, the
contractual terms do not include payment for
standard materials or “generic” component parts that
were specifically acquired for the project but not
yet incorporated into the customized machine.
That is, if the raw materials or
work in process has an alternative use before being
integrated into the manufacturing process, the raw
materials or work in process would not be considered
costs of the contract until integrated into the
manufacturing process. Consequently, the materials
or work in process does not transfer to the customer
until (1) integration of the materials or work in
process into the project and (2) the entity has an
enforceable right to payment.
Therefore, the absence of a right to
payment for raw materials or work in process that
has an alternative use does not preclude an entity
from being able to conclude that a performance
obligation is satisfied over time when the entity
has an enforceable right to payment for performance
completed to date once the entity has integrated the
raw materials or work in process into the project.
Accordingly, X’s contract with Y meets the condition
in ASC 606-10-25-27(c) for recognition of revenue
over time.
Connecting the Dots
An entity that has entered into a contract to manufacture customized goods may conclude
that the goods have no alternative use. In addition, depending on the payment terms of the
contract for customized goods, the entity may be required to recognize revenue over time. In
this arrangement, the entity will need to carefully consider the contract’s payment terms to
determine the appropriate recognition of revenue. Specifically, the entity may need to consider
termination provisions in the arrangement and how they interact with the entity’s right to
payment. For example, if the entity has some rights to payment for its performance, but the
contract has a termination provision that allows the customer to cancel at any time with no
obligation to pay the entity for work performed under the contract, the entity may not meet
the criteria for recognizing revenue over time because it has not met the right to payment
requirement.
ASC 606-10
Example 14 — Assessing Alternative Use and Right to Payment
55-161 An entity enters into a contract with a customer to provide a consulting service that results in the entity
providing a professional opinion to the customer. The professional opinion relates to facts and circumstances
that are specific to the customer. If the customer were to terminate the consulting contract for reasons other
than the entity’s failure to perform as promised, the contract requires the customer to compensate the entity
for its costs incurred plus a 15 percent margin. The 15 percent margin approximates the profit margin that the
entity earns from similar contracts.
55-162 The entity considers the criterion in paragraph 606-10-25-27(a) and the guidance in paragraphs
606-10-55-5 through 55-6 to determine whether the customer simultaneously receives and consumes the
benefits of the entity’s performance. If the entity were to be unable to satisfy its obligation and the customer
hired another consulting firm to provide the opinion, the other consulting firm would need to substantially
reperform the work that the entity had completed to date because the other consulting firm would not have
the benefit of any work in progress performed by the entity. The nature of the professional opinion is such
that the customer will receive the benefits of the entity’s performance only when the customer receives the
professional opinion. Consequently, the entity concludes that the criterion in paragraph 606-10-25-27(a) is not
met.
55-163 However, the entity’s performance obligation meets the criterion in paragraph 606-10-25-27(c) and is a
performance obligation satisfied over time because of both of the following factors:
- In accordance with paragraphs 606-10-25-28 and 606-10-55-8 through 55-10, the development of the professional opinion does not create an asset with alternative use to the entity because the professional opinion relates to facts and circumstances that are specific to the customer. Therefore, there is a practical limitation on the entity’s ability to readily direct the asset to another customer.
- In accordance with paragraphs 606-10-25-29 and 606-10-55-11 through 55-15, the entity has an enforceable right to payment for its performance completed to date for its costs plus a reasonable margin, which approximates the profit margin in other contracts.
55-164 Consequently, the
entity recognizes revenue over time by measuring the
progress toward complete satisfaction of the
performance obligation in accordance with paragraphs
606-10-25-31 through 25-37 and 606-10-55-16 through
55-21.
Example 16 — Enforceable Right to
Payment for Performance Completed to Date
55-169 An entity enters into
a contract with a customer to build an item of
equipment. The payment schedule in the contract
specifies that the customer must make an advance
payment at contract inception of 10 percent of the
contract price, regular payments throughout the
construction period (amounting to 50 percent of the
contract price), and a final payment of 40 percent
of the contract price after construction is
completed and the equipment has passed the
prescribed performance tests. The payments are
nonrefundable unless the entity fails to perform as
promised. If the customer terminates the contract,
the entity is entitled only to retain any progress
payments received from the customer. The entity has
no further rights to compensation from the
customer.
55-170 At contract inception,
the entity assesses whether its performance
obligation to build the equipment is a performance
obligation satisfied over time in accordance with
paragraph 606-10-25-27.
55-171 As part of that
assessment, the entity considers whether it has an
enforceable right to payment for performance
completed to date in accordance with paragraphs
606-10-25-27(c), 606-10-25-29, and 606-10- 55-11
through 55-15 if the customer were to terminate the
contract for reasons other than the entity’s failure
to perform as promised. Even though the payments
made by the customer are nonrefundable, the
cumulative amount of those payments is not expected,
at all times throughout the contract, to at least
correspond to the amount that would be necessary to
compensate the entity for performance completed to
date. This is because at various times during
construction the cumulative amount of consideration
paid by the customer might be less than the selling
price of the partially completed item of equipment
at that time. Consequently, the entity does not have
a right to payment for performance completed to
date.
55-172 Because the entity
does not have a right to payment for performance
completed to date, the entity’s performance
obligation is not satisfied over time in accordance
with paragraph 606-10-25-27(c). Accordingly, the
entity does not need to assess whether the equipment
would have an alternative use to the entity. The
entity also concludes that it does not meet the
criteria in paragraph 606-10-25-27(a) or (b), and,
thus, the entity accounts for the construction of
the equipment as a performance obligation satisfied
at a point in time in accordance with paragraph
606-10-25-30.
Example 17 — Assessing Whether a
Performance Obligation Is Satisfied at a Point in
Time or Over Time
55-173 An entity is
developing a multi-unit residential complex. A
customer enters into a binding sales contract with
the entity for a specified unit that is under
construction. Each unit has a similar floor plan and
is of a similar size, but other attributes of the
units are different (for example, the location of
the unit within the complex).
Case A — Entity Does Not Have an
Enforceable Right to Payment for Performance
Completed to Date
55-174 The customer pays a
deposit upon entering into the contract, and the
deposit is refundable only if the entity fails to
complete construction of the unit in accordance with
the contract. The remainder of the contract price is
payable on completion of the contract when the
customer obtains physical possession of the unit. If
the customer defaults on the contract before
completion of the unit, the entity only has the
right to retain the deposit.
55-175 At contract inception,
the entity applies paragraph 606-10-25-27(c) to
determine whether its promise to construct and
transfer the unit to the customer is a performance
obligation satisfied over time. The entity
determines that it does not have an enforceable
right to payment for performance completed to date
because until construction of the unit is complete,
the entity only has a right to the deposit paid by
the customer. Because the entity does not have a
right to payment for work completed to date, the
entity’s performance obligation is not a performance
obligation satisfied over time in accordance with
paragraph 606-10-25-27(c). Instead, the entity
accounts for the sale of the unit as a performance
obligation satisfied at a point in time in
accordance with paragraph 606-10-25-30.
Case B — Entity Has an
Enforceable Right to Payment for Performance
Completed to Date
55-176 The customer pays a
nonrefundable deposit upon entering into the
contract and will make progress payments during
construction of the unit. The contract has
substantive terms that preclude the entity from
being able to direct the unit to another customer.
In addition, the customer does not have the right to
terminate the contract unless the entity fails to
perform as promised. If the customer defaults on its
obligations by failing to make the promised progress
payments as and when they are due, the entity would
have a right to all of the consideration promised in
the contract if it completes the construction of the
unit. The courts have previously upheld similar
rights that entitle developers to require the
customer to perform, subject to the entity meeting
its obligations under the contract.
55-177 At contract inception,
the entity applies paragraph 606-10-25-27(c) to
determine whether its promise to construct and
transfer the unit to the customer is a performance
obligation satisfied over time. The entity
determines that the asset (unit) created by the
entity’s performance does not have an alternative
use to the entity because the contract precludes the
entity from transferring the specified unit to
another customer. The entity does not consider the
possibility of a contract termination in assessing
whether the entity is able to direct the asset to
another customer.
55-178 The entity also has a
right to payment for performance completed to date
in accordance with paragraphs 606-10-25-29 and
606-10-55-11 through 55-15. This is because if the
customer were to default on its obligations, the
entity would have an enforceable right to all of the
consideration promised under the contract if it
continues to perform as promised.
55-179 Therefore, the terms
of the contract and the practices in the legal
jurisdiction indicate that there is a right to
payment for performance completed to date.
Consequently, the criteria in paragraph
606-10-25-27(c) are met, and the entity has a
performance obligation that it satisfies over time.
To recognize revenue for that performance obligation
satisfied over time, the entity measures its
progress toward complete satisfaction of its
performance obligation in accordance with paragraphs
606-10-25-31 through 25-37 and 606-10-55-16 through
55-21.
55-180 In the construction of
a multi-unit residential complex, the entity may
have many contracts with individual customers for
the construction of individual units within the
complex. The entity would account for each contract
separately. However, depending on the nature of the
construction, the entity’s performance in
undertaking the initial construction works (that is,
the foundation and the basic structure), as well as
the construction of common areas, may need to be
reflected when measuring its progress toward
complete satisfaction of its performance obligations
in each contract.
Case C — Entity Has an
Enforceable Right to Payment for Performance
Completed to Date
55-181 The same facts as in
Case B apply to Case C, except that in the event of
a default by the customer, either the entity can
require the customer to perform as required under
the contract or the entity can cancel the contract
in exchange for the asset under construction and an
entitlement to a penalty of a proportion of the
contract price.
55-182 Notwithstanding that
the entity could cancel the contract (in which case
the customer’s obligation to the entity would be
limited to transferring control of the partially
completed asset to the entity and paying the penalty
prescribed), the entity has a right to payment for
performance completed to date because the entity
also could choose to enforce its rights to full
payment under the contract. The fact that the entity
may choose to cancel the contract in the event the
customer defaults on its obligations would not
affect that assessment (see paragraph 606-10-55-13),
provided that the entity’s rights to require the
customer to continue to perform as required under
the contract (that is, pay the promised
consideration) are enforceable.
The example below illustrates the determination of whether
and, if so, how to recognize revenue from real estate sales and purchase
agreements entered into before the completion of a property project.
Example 8-4
Entity A, a real estate developer,
entered into sales and purchase agreements with
various buyers before the completion of a property
project. The properties are located in Country B.
The sales and purchase agreements include the
following key terms:
-
A specific unit is identified in the contract.
-
Entity A is required to complete the property in all respects in compliance with the conditions set out in the sales agreement and the related building plans within two years from the time when the sales contracts are entered into.
-
The property remains at A’s risk until delivery.
-
The buyer is not permitted at any time before delivery to sub-sell the property or transfer the benefit of the agreement. However, the buyer can at any time before the date of assignment mortgage the property to finance the acquisition of the property.
-
The agreement specifies that the sales agreement can be canceled only when both the buyer and A agree to do so — in effect, the buyer does not have the right to cancel the sales agreement.
-
If both the buyer and A agree to cancel the contract, A has the right to retain 10 percent of the total purchase price, and the buyer is required to pay for all necessary legal and transaction costs incurred by A in relation to the cancellation.
-
If A fails to complete the development of the property within the specified two-year period, the buyer has the right to rescind the sales contract and A is required to repay to the buyer all amounts paid by the buyer together with interest. Otherwise, the buyer does not have a right to cancel the contract.
-
The purchase consideration is payable as follows:
-
5 percent of the entire sale consideration upon entering into the sales agreement.
-
5 percent of the purchase consideration within one month from the date when the sales agreement is entered into.
-
5 percent of the purchase consideration within three months from the date when the sales agreement is entered into.
-
The remaining 85 percent of the purchase consideration upon delivery of the property.
-
Note that for simplicity, this
example does not address whether there is a
significant financing component.
Under ASC 606, an entity satisfies a
performance obligation over time when it transfers
control of the promised good or service over time.
ASC 606-10-25-27 states that an entity transfers
control of a good or service over time and,
consequently, satisfies a performance obligation and
recognizes revenue over time if one of the following
criteria is met:
-
The customer simultaneously receives and consumes the benefits provided by the entity’s performance as the entity performs . . . .
-
The entity’s performance creates or enhances an asset (for example, work in process) that the customer controls as the asset is created or enhanced . . . .
-
The entity’s performance does not create an asset with an alternative use to the entity . . . , and the entity has an enforceable right to payment for performance completed to date.
Criterion (a) above is not relevant
in the determination of whether revenue from real
estate sales (before completion) should be
recognized over time or at a point in time. This is
because buyers generally do not consume all of the
benefits of the property as the real estate
developers construct the property; rather, those
benefits are consumed in the future.
Criterion (b) above is not directly
relevant either because, without further
consideration of criterion (c), a conclusion cannot
be reached about whether the buyers have control of
the property as A develops the property. For
example, property buyers may not obtain physical
possession of or title to the property until
construction is completed.
Entity A should focus on criterion
(c), and particularly on (1) whether an asset has
been created with an alternative use to the real
estate developer and (2) whether the real estate
developer has an enforceable right to payment for
performance completed to date.
Has an Asset
Been Created With an Alternative Use to Entity
A?
In accordance with ASC 606-10-25-28,
an asset does not have an alternative use to an
entity if the entity is either restricted
contractually from readily directing the asset for
another use during the creation or enhancement of
that asset or limited practically from readily
directing the asset in its completed state for
another use.
With regard to contract restriction,
ASC 606-10-55-8 states that the entity does not
consider the possibility of a contract termination
in assessing whether the entity is able to direct
the asset to another customer.
Since each sales contract specifies
the unit to be delivered, the property unit does not
have an alternative use to A. The contract precludes
A from transferring the specified unit to another
customer.
Does Entity A
Have an Enforceable Right to Payment for
Performance Completed to Date?
The payment schedule per the sales
and purchase agreement does not correspond to the
performance completed to date. However, in assessing
whether it has the right to payment for performance
completed to date, A should not only consider the
payment schedule but should also consider ASC
606-10-55-13, which states:
In
some contracts, a customer may have a right to
terminate the contract only at specified times
during the life of the contract or the customer
might not have any right to terminate the
contract. If a customer acts to terminate a
contract without having the right to terminate the
contract at that time (including when a customer
fails to perform its obligations as promised), the
contract (or other laws) might entitle the entity
to continue to transfer to the customer the goods
or services promised in the contract and require
the customer to pay the consideration promised in
exchange for those goods or services. In those
circumstances, an entity has a right to payment
for performance completed to date because the
entity has a right to continue to perform its
obligations in accordance with the contract and to
require the customer to perform its obligations
(which include paying the promised
consideration).
In the circumstances under
consideration, the contract specifies that the
customer cannot terminate the contract unless both
the property developer and the buyer agree to do so.
In effect, the buyer does not have the discretion to
terminate the contract as it wishes.
ASC 606-10-25-28 requires an entity
to consider the terms of the contract, as well as
any laws that apply to the contract, when evaluating
whether it has an enforceable right to payment for
performance completed to date. If, taking into
account practice and legal precedent in Country B, A
has the right to continue to perform the contract
and be entitled to all of the consideration as
promised, even if the buyer acts to terminate the
contract (as articulated in ASC 606-10-55-13 and ASC
606-10-55-88), A has the enforceable right to
payment for performance completed to date.
The same response (i.e., the
recognition of revenue over time) applies
irrespective of whether A allows buyers to choose to
pay the consideration on the basis of the
agreed-upon payment schedule or to pay all of the
consideration up front.
Should Entity A
Recognize Revenue Over Time or at a Point in
Time?
Since the asset does not have an
alternative use to A, and provided that A has an
enforceable right to payment for performance
completed to date, it should recognize revenue over
time. However, if A does not have an enforceable
right to payment for the performance completed to
date, it should recognize revenue at a point in time
(i.e., at the point when the control of the property
unit is transferred to the buyer, which would
normally be at the time of delivery).
8.4.5.2.1 How and When an Entity Should Determine Whether It Has an Enforceable Right to Payment
In Implementation Q&A 56 (compiled
from TRG Agenda Papers 56 and
60), the FASB staff discusses how
and when an entity should determine whether it has an enforceable right
to payment under ASC 606-10-25-27(c). The staff notes that under ASC
606-10-55-14, an entity should consider the following factors in
addition to assessing the terms of the contract:
-
“[L]egislation, administrative practice, or legal precedent that confers upon the entity a right to payment for performance to date even though that right is not specified in the contract with the customer.”
-
“[R]elevant legal precedent that indicates that similar rights to payment for performance completed to date in similar contracts [have] no binding legal effect.”
-
An “entity’s customary business practice of choosing not to enforce a right to payment that has resulted in the right being rendered unenforceable in that legal environment.”
The determination should be made at contract inception.
To illustrate its analysis, the FASB staff provides the following
example:
For each of the last five years, an entity has
received an order from a customer for 300 custom ice cream
machines. The specifications of the ice cream machines are
unique to the customer. In anticipation of the customer’s order
this year, the entity starts production of the custom ice cream
machines before there is a contract between the parties in the
current year. The entity is willing to take the risk of
beginning to manufacture custom units before there is a contract
because (a) the customer has predictable purchasing behavior and
(b) the entity has knowledge of the customer’s performance in
the current year and plans for growth from the customer’s public
disclosures. The entity and the customer later enter into a
contract (that meets all of the criteria in Step 1 of Topic 606)
for 300 units. The entity has a practical limitation on its
ability to direct the equipment in its completed state because
it could not do so without incurring a significant economic
loss. The entity has an enforceable right to payment beginning
when the contract is executed. Assume that each of the machines
is distinct. At the inception of the contract, the entity has
completed 50 units (that is, 50 units are in inventory awaiting
shipment to the customer), has 10 units in production (that is,
10 units are in various stages of the manufacturing process),
and has not begun manufacturing 240 units.
The staff concludes that at contract inception, the
performance obligation to transfer 300 units meets the criteria for
recognizing revenue over time because (1) the ice cream machines do not
have an alternative use to the entity (i.e., because significant rework
would be needed to redirect the assets to another customer) and (2) the
entity has an enforceable right to payment for progress completed to
date. Although the entity did not have an enforceable right to payment
when it was customizing the ice cream machines in anticipation of a
customer order, the criteria were met as soon as a valid and genuine
contract existed. Consequently, the performance obligation to transfer
300 units to the customer is satisfied over time in accordance with ASC
606-10-25-27(c).
In the staff’s example, the entity also meets the
requirements in ASC 606-10-25-14 and 25-15 to account for the transfer
of the 300 units as a series of distinct goods or services that
constitute a single performance obligation. The entity would record (1)
a cumulative catch-up adjustment to revenue to reflect its progress
toward complete satisfaction of its performance obligation to transfer
300 units to its customer and (2) revenue for 50 completed and 10
in-process ice cream machines that will be transferred to the customer
once the new contract is executed.
8.4.5.2.2 Impact of Intent and Past Practice on Enforceable Right to Payment
As discussed in ASC 606-10-25-27(c), revenue from a
contract should be recognized over time if the “entity’s performance
does not create an asset with an alternative use to the entity . . . and
the entity has an enforceable right to payment for performance completed
to date.” This concept is further discussed in ASC 606-10-55-13, which
states, in part:
If a customer acts to terminate a contract
without having the right to terminate the contract at that time
(including when a customer fails to perform its obligations as
promised), the contract (or other laws) might entitle the entity to continue to transfer to the
customer the goods or services promised in the contract and
require the customer to pay the consideration promised in
exchange for those goods or services. In those
circumstances, an entity has a right to payment for performance
completed to date because the entity has a right to continue to
perform its obligations in accordance with the contract and to
require the customer to perform its obligations (which include
paying the promised consideration). [Emphasis added]
An entity may have an established practice of not
enforcing its contractual or legal rights (e.g., not continuing to
transfer the goods or services for which it could seek payment, not
seeking a reimbursement in excess of cost, not collecting a penalty from
the customer), or it may assert that it has no intention of enforcing
its contractual or legal rights.
However, an entity generally should not consider
its intent or past practice related to the enforcement of contractual or
legal rights when performing an evaluation under ASC 606-10-25-29 to
determine whether the enforceable right to payment criterion in ASC
606-10-25-27(c) is met. The determination of whether an enforceable
right to payment exists is evaluated under the terms of the contractual
arrangement as a matter of law. An entity’s intent or past practice
related to the enforcement of contractual or legal rights should be
considered only if the intent or past practice has created a legal
precedent as a matter of law that negates the enforceable right in a
contract.
This is consistent with ASC 606-10-25-29, which states,
in part:
An entity shall consider the terms of the
contract, as well as any laws that apply to the contract, when
evaluating whether it has an enforceable right to payment for
performance completed to date in accordance with paragraph
606-10-25-27(c).
ASC 606-10-55-14 provides additional insight into the
application of ASC 606-10-25-29. It states, in part, that the assessment
of whether an entity has an enforceable right to payment should take
into account whether:
-
Legislation, administrative practice, or legal precedent confers upon the entity a right to payment for performance to date even though that right is not specified in the contract with the customer.
-
Relevant legal precedent indicates that similar rights to payment for performance completed to date in similar contracts have no binding legal effect.
-
An entity’s customary business practices of choosing not to enforce a right to payment has resulted in the right being rendered unenforceable in that legal environment.
The above issue is addressed in Implementation Q&A 56 (compiled
from TRG Agenda Papers 56 and
60). For additional information and
Deloitte’s summary of issues discussed in the Implementation Q&As,
see Appendix
C.
Connecting the Dots
ASC 606-10-25-29 provides that an “entity shall
consider the terms of the contract, as well
as any laws that apply to the contract, when evaluating
whether it has an enforceable right to payment for performance
completed to date in accordance with paragraph 606-10-25-27(c)”
(emphasis added). In practice, it may be uncommon for an entity
to pursue legal action against a customer if the customer
canceled a contract, especially when there is an ongoing
customer-vendor relationship. That is, entities may elect not to
enforce their legal right to payment.
For example, suppose that Company A and Customer
M have a long-standing relationship. Although A may have a legal
right to recover its costs plus a reasonable profit margin if M
terminates a contract, A and M may intend to negotiate a
settlement to preserve the relationship in the event that a
contract is terminated. Regardless of the likelihood that A
would enforce its right to full payment from M, the criterion in
ASC 606-10-25-27(c) is met as long as A has a legally
enforceable right to payment that includes recovery of its costs
plus a reasonable profit margin.
In addition to the above, entities should
consider instances in which their past practice has rendered
their right to payment unenforceable.
8.4.5.2.3 Whether an Entity Has an Enforceable Right to Payment Upon Contract Termination When No Such Right Is Specified in the Contract
Questions about the application of ASC 606-10-55-14(a)
or (b) may arise when an entity creates a good with no alternative use
and the written terms of the contract with the entity’s customer do not
specify the entity’s right to payment upon contract termination. For
example, this situation could occur in the United States, where the
Uniform Commercial Code (UCC) or a state equivalent of the UCC is
applied upon contract termination.
We believe that when a contract’s written terms do not
specify the entity’s right to payment upon contract termination, an
enforceable right to payment for performance completed to date is
presumed not to exist.
However, if the contract with the customer does not
specify by its written terms the entity’s right to payment upon contract
termination and the entity asserts that it has an enforceable right to
payment for performance completed to date, we would expect the entity
to:
-
Support its assertion on the basis of legislation, administrative practice, or legal precedent that confers upon the entity a right to payment for performance to date, as stated in ASC 606-10-55-14(a). This analysis would need to demonstrate that an enforceable right to payment (as defined by ASC 606) exists in the relevant jurisdiction. The fact that the entity would have a basis for making a claim against the counterparty in a court of law would not be sufficient to support the existence of an enforceable right to payment.
-
Assess whether relevant legal precedent indicates that similar rights to payment for performance completed to date in similar contracts have no binding legal effect, as stated in ASC 606-10-55-14(b).
8.4.5.2.4 Impact of Shipping Terms on Revenue Recognition Over Time
Shipping terms in a contract that require a customer to
pay only at a specific point in time (e.g., “free on board” [FOB]
destination) do not preclude the contract from meeting the criterion in
ASC 606-10-25-27(c) for revenue recognition over time (specifically, the
enforceable right to payment condition).
The guidance in ASC 606-10-55-12 makes clear that an
enforceable right to payment “need not be a present unconditional right
to payment” and that an entity may have “an unconditional right to
payment only . . . upon complete satisfaction of the performance
obligation.” In these circumstances, the guidance states, “an entity
should consider whether it would have an enforceable right to demand or
retain payment for performance completed to date if the contract were to
be terminated before completion for reasons other
than the entity’s failure to perform as promised” (emphasis
added).
When a contract’s shipping terms require an entity’s
customer to pay only at a specific point in time (e.g., FOB
destination), the possibility that the entity will not be paid if the
goods are lost in shipment would represent “the entity’s failure to
perform as promised” and should be disregarded in the entity’s
assessment of whether the performance obligation meets the criterion in
ASC 606-10-25-27(c) for revenue recognition over time (i.e., when an
entity is assessing whether it has an enforceable right to payment, it
should presume that it will perform as promised and that the goods will
be delivered). Accordingly, the conclusion that the entity has an
enforceable right to payment is not precluded when the contract’s
payment terms require payment only at specific points in the production
or delivery process. Those payment terms may be overruled by contractual
rights that give the entity an enforceable right to demand or retain
payment (if the entity performs as promised). Therefore, the fact that
the customer would not be required to pay for the goods if they were
lost in transit would not, by itself, preclude the contract from meeting
the criterion in ASC 606-10-25-27(c) for revenue recognition over
time.